Chandlee Construction Company performed a repair project for PIER 1 IMPORTS under the supervision of Jeremy Rowe, Field Operator for Chandlee Construction. The scope of this project was the removal of an acoustic ceiling and the replacement of a 4 inch water pipe that was 80 feet long.
This project was coordinated between the Retail Planning Group, Art Plumbing and Chandlee Construction. As of May 2 Phase One of this project was complete. The acoustical ceiling was removed and the rooms were cleared for the plumbers to have access to the pipes.
The following day ART Plumbing was on site to complete Phase Two – the removal and replacement of an 80 foot piece of pipe. The old pipe was leaking water from a mop sink inside the Tuesday Morning store into the Pier 1 Imports space. The project was quickly and successfully completed.
This Pier 1 Imports in located in Suite 100 at 3101 Cobb Parkway in Atlanta. Their Facebook page can be viewed at https://www.facebook.com/Pier1AtlantaGA1214/.